Main About Laser Critic Search Disclaimer FPC What's NEW

 

Litigation
These suits were found in Summit County and Federal court. LASER will be searching other courts and areas to achieve a clearer picture of Moser’s litigation history.

THREE CONSTRUCTION CUSTOMERS OF MOSER CHARGE THAT MOSER PERFORMED FAULTY AND INCOMPLETE WORK

MOSER CONSTRUCTION COMPANY, INC. V WESTRA CONSTRUCTION, INC.

At first blush, this is a case of Moser Construction filing a lien and then suing a deadbeat customer. Moser sought to collect unpaid debts of $61,157 from Westra Construction for a 1998 construction project of Outlook Pointe, an assisted living community center at Ravenna in Portage County, Ohio.

But here is Westra Construction’s version of events, taken from their response filed with the courts:

"Westra subcontracted with Moser for the provision of materials and labor for masonry, foundation and flat concrete work in the construction of Outlook Pointe. Unfortunately, some of Moser’s work was not acceptable and Westra back-charged Moser for the cost of repairing or redoing that work … In addition, Westra disputes some of Moser’s invoices for extra work and finance charges."

In other words, there are allegations of a hidden story behind Moser’s lien and court suit – namely that the construction customer found Moser’s work unsatisfactory and their bills inflated.

This is not the only court suit in which unhappy construction customers have charged that Moser Construction’s work was unsatisfactory.

R & M ELECTRIC COMPANY , INC. V MOSER CONSTRUCTION COMPANY INC.

According to the lawsuit, R & M Electric (doing business as Summit Electric) was the successful bidder for the City of Akron’s field lighting contract for the renovation of the Firestone Stadium in November 1998. R&M subcontracted the excavation portion of the contract to Moser Construction for $12,540.

Moser Construction did not start their portion of the work until December 23, 1998, the day before Christmas Eve.  Alarmed city officials warned that they needed several portions of the excavation work completed by January 14, 1999 or they would hire their own contractor and then back-charge R & M Electric for those expenses.

According to R&M Electric’s civil court complaint, Moser Construction failed to complete the conduit excavation and backfilling on time. The city had to hire another excavation contractor and they billed R&M Electric for those additional costs of $6,194.

Furthermore, R&M Electric charged that Moser Construction "negligently" built a concrete pad for the placement of an electrical panel "that was not level" and "not of workmanlike quality." The City of Akron did not accept the pad and R&M Electric said they had to correct the pad’s defects and pay for the improvements out of their own pocket.

Finally, Moser Construction was supposed to auger a series of holes and set casings and concrete bases for a series of new light poles, but according to R&M Electric

"[Moser Construction] never returned to the job after it failed to perform the work ... and therfore breached its contract for failing to install the new and prefab light pole bases..."

R&M Electric’s complaint also states that Moser Construction breached its contract by failing to remove the old light pole foundations and by failing to saw cut and remove old concrete pavement outside the stadium. In sum, R&M Electric sued Moser Construction for over $41,000 for breach of contract.

Moser Construction admitted they did not complete the work and responded that the soil they were supposed to excavate was too rocky and that they also did "extra" work. Moser filed a Claim against Funds against the City of Akron, seeking compensation of $6,258 for the work they did complete. The case was ultimately settled and dismissed.

But these are not the only two cases in which construction customers of Moser have claimed that Moser provided faulty and incomplete work. Below is yet another recent example, filed in 2000, where the customer charged that Moser’s products and services were unacceptable.

MOSER CONSTRUCTION COMPANY, INC. V W&W DEVELOPMENT, VALLEY HIGH PROPERTY, LTD., SUMMIT COUNTY TREASURER, PARK VIEW FEDERAL SAVINGS BANK, GREIF BROS. CORP.

According to court documents, Valley High Property originally hired Moser Construction in late 1998 and 1999 to provide goods and services during the construction of the Flex Office-Warehouse Development in Macedonia, Ohio. Moser claimed that they provided $18,924 in products and labor to the project, but were not paid. So Moser Construction filed another damaging mechanic’s lien against the property and then filed a court suit not only against Valley High, but against another party, W & W Development.

But W & W Development and Valley High submitted a Statement of Facts and an Answer that conflicted sharply with Moser Construction’s assertions. According to their Statement and Answer:

"[Moser Construction], in breach and contravention of this contract with Valley High, failed to provide the furnished products and services relative to the project in a timely, acceptable and workman-like manner. As a result [ of Moser’s breach of contract], Valley High has sustained damages that are expected to exceed any amount [$18,000] allegedly owed to [Moser].

The following issues are to be determined at the trial of this matter: Whether [Moser] breached its agreement with Valley High ... Whether [Moser] negligently provided and furnished services ... [In addition], W&W is not a proper party to this action ... W&W is also expected to file a counterclaim [against Moser] alleging frivolous conduct and abuse of process claims."

Moser Construction later dismissed W & W from the suit.

Back Critic Up Next