Main About Laser Critic Search Disclaimer FPC What's NEW

 

March-Westin Company, Inc., Issue No. 2

January 2002

The Contractors Critic
March-Westin company, Inc.

Reporting on Safety, Productivity, and Honesty in the Construction Industry.

Questionable Work & Safety Violations

Many Problems Documented at multiple Job Sites for West Virginia University Hospital

One of March-Westin Company’s most visible jobs in Morgantown, West Virginia was the work on West Virginia University Hospital’s (WVH) "Family House." March-Westin also had large jobs for WVH on the Eye Institute and the HealthWorks buildings. Under the public records act, The Contractor’s Critic has been able to obtain written documents that indicate that all did not go well on these jobs.

In the following narratives, March-Westin may not be solely at fault for the problems that are discussed. But March-Westin proudly touts these and other construction jobs as their "projects," on the March-Westin web site. In the Critic’s opinion, if March-Westin wants the credit for building these projects, then they should not complain when the blame is spread around for the projects’ delays and problems.

The Contractors Critic has tried to be as specific as possible in determining if March-Westin deserves any of the blame for the problems that are listed below, or if one of their subcontractors is the real culprit. Even then, to the degree that March-Westin was a general contractor and/or construction manager on these projects, they bear the responsibility for the misdeeds on these projects. Finally, the materials released under the Freedom of Information Act often contain marked-out portions that made these documents hard to decipher. Where March-Westin Company is specifically mentioned, we have tried to include those references. The following is a list of some specific problems.

Problems on this job ranged from the fire protection system to the door locks, as well as a persistent problem with rainwater seeping under the doors and through the roof causing extensive damage.

According to June 2001 e-mails from Robert Carubia of WVH, the jack on the Family House elevator also sprung a fairly substantial leak. The university was concerned that they would be forced to shut the elevator down.

Also in June 2001, an e-mail titled "rain issues" complained that the sills at the outside hospital doors "are suspect" and possibly leaking in rainwater.

Apparently the drainage around the doors had become a problem earlier, according to May 2001 e-mails to both WVH and March-Westin Company. "The heavy rains flood the wells in front of the doors and since there is no vertical stop on the thresholds ... (of the doors) the water will go under the doors. The only solution ... is to cut the concrete at the door openings and put in a trench drain."

The water infiltration appeared to be the worst at the doorway to the 3rd floor kitchen and stairway. There were claims of disruption and extra clean-up efforts that have accelerated to floor damage, including the tiles and wood strip flooring. The emergency mopping had become a problem all of its own, and there was a threat of damage on top of the fan coil unit, as well.

Those problems had been noticed for months. An inspection found that the vertical stiles were beveled and did not meet closely, so that a driving rain could get behind the weather stripping. Also the concrete did not slope away from the door, and a heavy rain could flood there and come over the threshold.

As much as 10 months earlier in August 1999, the hospital complained, "We discovered there is still much water coming into the 3rd floor kitchen of the Family House. Is this still a March-Westin issue?" March-Westin had claimed it was a caulking problem that had been corrected, but apparently the problem continued.

Not only did the doors leak, there was a leaking roof noted in June 1999. The leak was severe enough to damage the ceiling, and also wrecked the television reception. The hospital thought that a coaxial cable might have been disconnected during the ceiling repairs. The hospital became so frustrated that they made a threat towards March-Westin stating that they would have someone else troubleshoot and correct the problem, and then "deduct the costs from the remaining contract sum. This ... has deteriorated our financial situation," the hospital complained to March-Westin.

There were also problems with non-payment of a March-Westin subcontractor, which caused lien’s to be filed against this job. March-Westin’s payment bond for the project was needed to resolve the matter.

New University Administrative Complex Unsettling

The Contractors Critic has found disturbing information about West Virginia University’s new Administrative Complex. After reviewing the city of Morgantown files in the Planning Department, Public Works, and City Engineers offices and interviewing workers who worked on the Administrative Complex, it appears that the complex may be out of plumb or in other words similar to the Leaning Tower of Pisa.

Triad Engineering, Inc. stated in a pre-construction report, "We conclude that the site and subsurface conditions are not suitable for use of conventional spread foundations bearing at minimal depths for the office building and parking garage. Most of the site is covered by alluvial clays and sands that, with the anticipated columns loads, could undergo excessive elastic and consolidation settlements. This could create some level of structural distress which is undesirable." Triad went on to suggest that a qualified engineering firm should be retained to provide continuous geo-technical engineering services during the foundation construction phases of the work. The Critic has not been able to confirm that March-Westin and/or the developer followed Triad Engineering’s advice.

As of publication, March-Westin Company has not made any suggestions or refuted any of the information in this publication.

Critic Up Next