Over the years, Ohio
State University has handed Danis Building Construction tens of millions of
dollars in construction contracts. According to Ohio State records obtained by
LASER under the State Public Records Act, on some jobs Danis has short changed
Ohio State on the quality of its work and Danis has fallen behind schedule and
misrepresented the status of its job.For instance, in
1998 and 1999 Danis Building Construction Company had a construction job at the
Fisher College of Business at Ohio State University in Columbus. During the
course of that contract, the architects who were overseeing the job for Ohio
State University had several battles with Danis. These architects from the firm
of Kallman, McKinnell & Wood Architect, Inc. clashed with Danis over Danis’
misrepresentation of the type of wood finish used on one portion of this job.
They clashed again when Danis misrepresented the status of the college building
masonry, Jack Arch repair work. The architects also had to issue several 72-hour
correction notices against Danis to force repair of the wood finish, to force
Danis to correct a pedestrian walk and a staircase, and to force Danis to
correct warped plastic laminate panels in classroom desks.
The university also had problems when Danis misled the
university about their ability to meet the project deadline. Another contractor
on this job, Gilbane, also complained in writing to the architect firm: "Danis’
response to the letter of May 7, 1998, also affirms that its work in the
telecommunication rooms was complete on May 1, 1998. That simply is not
true. I continue to receive requests from Danis to open the
telecommunication rooms so that Danis ... can complete their work ... after the
rooms were cleaned ... deficiencies became visible. Danis has failed to fulfill
(its) requirement(s)."
Ohio State also had problems with dust from Danis’ job site
and Danis’ inability to meet the completion schedule for Phase I of the Fisher
College of Business job. Jill Morelli, an Assistant Vice President and Architect
for Ohio State, wrote to Danis on April 10, 1998 and complained: "I am very
distressed to learn that the completion schedule for Phase I of the Fisher
College of Business has slipped again. Surely the university should have been
able to rely on the word ... of ... experienced contractors. As a result of not
meeting that schedule, the university will incur additional costs. We cannot
tolerate these additional delays."
Ultimately, Ohio State University rated Danis less than
satisfactory for their ability to interpret plans and specifications and their
timeliness in making decisions relating to the project.
The allegations about Danis failing to meet the contract
specifications on the wood finishing job and then lying about it, arose in April
1999, according to the Kallman, McKinnell & Wood, architect firm, correspondence
to Danis regarding this matter. Part of that work at the Fisher School of
Business included architectural woodwork finish that was supposed to be done to
contract specifications. According to their letter, not only did Danis and its
millwork subcontractor fail to use the specified wood finish on the woodwork for
the dean’s suite, but also according to the job’s architects, Danis and its
subcontractor lied about the type of finish that was actually applied.
The university only discovered that Danis and its
subcontractor had falsified its answers regarding the finish on the woodwork, by
conducting its own special testing of the materials. On April 9, 1999 the firm
of Kallman, McKinnell & Wood Architect, Inc. wrote a strongly worded letter to
Mark Davis of Danis Building Construction Company. The letter stated: "The
contract requires that Danis provided the products and materials specified. (But
Danis) presented shop drawings, mockups and wood samples for review and approval
without pointing out that what it was presenting was not what was specified. It
wasn’t until the design team reviewed the dean’s suite punch list with Danis and
its millwork contractor that Ted Bolle revealed (the truth)."
"Yes, we were suspicious when the sheets we received from
Danis contained conversion varnish and catalyzed lacquer data sheets. The
associate requested a clarification from Danis. There never was a response from
Danis."
"Consequently, since Danis refused to share with the associate
the information it had about the use of the two finishes, the provision for
special testing was invoked. Now that the special testing is complete ... we
know that Danis’ statement ... on all the millwork was not true."
"Danis states the difference ... is insignificant. The
associate takes strong exception to Danis’ attitude. (Danis’) arbitrary decision
making, a practice not allowed by the contract, is not what we expect from a
responsible contractor. By contract, the cost of the special testing is Danis’
to pay."
Ohio State University did not consider the difference between
the contracted work for the wood finish and what Danis attempted to pass on to
the university, to be insignificant. The Kallman, McKinnell & Wood firm
ultimately sent Danis angry letters, including a 72-hour notice for correction
of work. Their letters stated: "This is to officially notify Danis Building
Construction Company that the finishing of the wood paneling located in the
dean’s suite is not acceptable and is, therefore, deemed … to be defective work.
Danis shall bear all costs of correcting such defective work, including the
costs of consequential damages. If Danis fails to correct the work, the state
may exercise its right to prosecute work and back charge the contractor."
"In accordance with Article 5.3 of the General Conditions, the
Associate is hereby giving written notice to the Danis Building Construction
Company to provide, within three working days after receipt of this notice, a
plan and schedule for correcting the entire finish on the wood paneling located
in the dean’s suite. If Danis fails or refuses to comply with this written
notice, the director shall, without prejudice to any other remedy ... employ
additional force to correct the deficiency in the contractor’s work. The
decision of the director to back charge the contractor shall be final." (Signed)
Richard G. Carpenter.
Another problem arose on this Danis job for Ohio State
University in November 1998. Phase I of the Fisher College of Business job
included repair of a masonry arch. All during the frequent meetings between the
architects, Danis told them that a special type of brick was scheduled for
delivery as part of completing that job. According to Richard G. Carpenter, AIA,
of the Kallman, McKinnell & Wood firm, Danis never informed the architect that
the special shapes, which were required for this job, could not be fabricated.
According to his November 9, 1998 letter: "At no time did ... Danis inform the
(architect firm) associate that the first try solution brick was not being
fabricated."
|
LASER finds another Lien
In August 1998, Danis performed construction work on the Oak Hills High School
in Cincinnati, Ohio. Danis hired CIC Company of Felicity, Ohio to do part of the
work. James Webb, a heavy equipment operator who worked for CIC did not get
paid. In order to collect his $4,560 in wages, he was forced to file a lien on
public funds with the Oak Hills School District. |