COBB MECHANICAL CONTRACTORS
SUES A FELLOW CONTRACTOR AND A CONSTRUCTION CUSTOMER
COBB MECHANICAL CONTRACTORS V SCHAUER CONSTRUCTION COMPANY,
JOSEPH A. FORTINO
Schauer Construction Company was bidding for work on the Pueblo
Convention Center, which was run by the Urban Renewal Authority of Pueblo,
Colorado. Initially, Schauer spoke to Cobb Mechanical Contractors about Cobb
bidding on the mechanical subcontract on this work and Cobb ultimately
submitted a verbal estimate. However, as the bidding process went on, an
Urban Renewal Authority told Schauer that they did not want Cobb Mechanical
Contractors on the job, according to Cobb’s court complaint. After checking
to see how many of Cobbs’s employees actually lived in Pueblo, where the job
would take place, Schauer called Cobb and told them they had been replaced.
Cobb sued, complaining that they were competent, that there was no
requirement to have its employees live near the project site and they were
not disbarred or suspended by the State of Colorado or any other federal
agency. As it turned out, Cobb Mechanical Contractors had been recently
disbarred from public works construction jobs by both the federal government
and the State of Colorado although the disbarment notices had run out just
scant months before bidding opened on for the Pueblo Convention Center.
It wasn’t enough for Cobb Mechanical Contractors to sue Schauer
Construction. They also sued Joseph A. Fortino, who was a member of the
Urban Renewal Authority.
MORE JOBS
GONE BAD THAT ENDED UP IN COURT— ADP MARSHALL’S COURT SUIT CLAIMS THAT COBB
ABANDONED A HIGH-TECH JOB IN COLORADO SPRINGS
COBB MECHANICAL CONTRACTORS V ADP/MARSHALL, LLC AND
SYMBIOS LOGIC INC.
ADP/Marshall hired Cobb Mechanical Contractors as a subcontractor for
$3.8 million in work on a state-of-the art high-tech Fab Plant expansion
construction job in Colorado Springs. ADP/Marshall, for their part were the
design/build contractor on the project, while Cobb was supposed to perform
the HVAC, sheet metal and plumbing work at the plant. But according to
ADP/Marshall’s court complaint:
"Cobb failed to comply with the contract documents in performing its
work on the project. ADP/Marshall repeatedly demanded that Cobb perform
its contractual obligations, but Cobb failed to comply with these
requests. Without cause or justification, Cobb failed to complete its
work on the project." The complaint further states, "Cobb breached its
obligations under the Cobb subcontract by ... failing to: repair and
replace ... its defective workmanship, begin, prosecute and complete the
subcontract work in a timely manner... [failing to] provide on the
project site a competent and experienced superintendent, [failing to]
comply with the subcontract’s prohibition against filing a mechanic’s
lien against the project, [failing to] pay its material supply
subcontractor, Mountain States Engineering, Inc... $31,910.50 ...
[failing to] complete its subcontract work and then abandoned the
project."
COBB’S DEBT
BRINGS ANOTHER LAWSUIT AGAINST A PROJECT MOUNTAIN
STATES ENGINEERING V ADP/MARSHALL, COBB MECHANICAL
CONTRACTORS, SYMBIOS LOGIC
These allegations of Cobb Mechanical Contractor’s problems on this job
are not limited to a single court suit. Cobb’s supplier, Mountain States
Engineering, also filed a separate suit, seeking the $31,911 that Cobb owed
them. Mountain States filed suit not only against Cobb, but also against
ADP/Marshall and the hapless project owner, Symbios Logic. Mountain States
also filed a lien again the project.
Their complaint stated that they provided over $160,000 in labor and
materials to Cobb Mechanical Contractors, but were only paid about $128,000.
Mountain States Engineering sought money from all these parties. In other
words, ADP/Marshall and Symbios Logic were both dragged into court, because
of allegations that Cobb Mechanical Contractors wasn’t paying their debts.
The fact that Cobb Mechanical Contractors may not have paid a $31,911
debt may not seem like a huge issue. But on a construction job, failure to
pay a supplier or subcontractor can have dire consequences, because those
parties can file a lien against the property of the construction customer.
In the case of Symbios Logic, that is exactly what happened.
Liens, like court suits, are an unnecessary evil in the construction
industry. Many construction customers know how maddening it is to try and
obtain bank financing where there is some claim or lien— no matter how
frivolous— against your property. That is why it is important for
construction customers to be concerned about whether a contractor is likely
to file liens against its customers, rather than negotiate a solution. A
lien against your property by a contractor is as effective a claim against
your equity as a bank’s mortgage, according to the Engineering News
Report.
In this case, not only does it appear that Cobb Mechanical Contractors
violated a "no-lien" clause in their contract, but Cobb’s unpaid supplier
also filed a lien. And then, not only were Cobb’s general contractor and
construction customer facing liens, they were also defending themselves in
court, not because of their own errors, but over allegations of Cobb’s
wrongdoing.
MORE BAD
DEBTS BY COBB MECHANICAL CONTRACTORS
DENSAND, INC. V COBB MECHANICAL CONTRACTORS
In light of the kinds of problems that Cobb Mechanical Contractors’s
debts can cause for construction customers, the following case takes on
troubling implications. In this action, Densand, a plumbing equipment
supplier, sued Cobb Mechanical Contractors for failing to pay for materials
supplied to seven different construction sites— the Shadow Mountain
Correctional Facility in Canyon City, Colorado, the Brighton District, the
Super K-Marts in Greeley and Greenwood Village, Colorado, the Dalhart and
the Amarillo Prisons in Texas and the Lewis Palmer Middle School job in
Monument, Colorado. Cobb claims that, "Densand provided Cobb with 10"
expansion joints which were defective and failed." Futhermore, Cobb stated
that, "Densand provided Cobb with pump seals for the... project" and that "[t]hese
seals also failed."
By failing to pay its supplier, Cobb Mechanical Contractors put all of
these projects at risk of liens, stop work orders in the case of a public
works job and lawsuits.
COBB
MECHANICAL CONTRACTORS CHARGED WITH MORE CONSTRUCTION DEFECTS
HEALTHONE V COBB MECHANICAL CONTRACTORS, HENSEL PHELPS
CONSTRUCTION, ROSS/WOU INTERNATIONAL, OTHERS
Healthone’s predecessor hired Cobb Mechanical Contractors and others to
build a new medical center, including a parking structure and snow melt
system, at 1601 E. 19th Avenue in Denver. Cobb Mechanical Contractors was
specifically charged with construction of the snow melt system.
But within two years after the project was completed, leaks were obvious
in the parking structure. There was evidence of drainage through various
de-icing and pipe penetrations in the walls and ceiling. Cobb Mechanical
Contractors and others came back and made repairs, but they refused to
reimburse the construction customer for the damages they had to pay to the
parking lot customers for the water damage from the leaks.
And six month later, an Engineering Report of the parking structure
concluded that the problems there were abnormal and indicated there were
construction defects. Cobb Mechanical Contractors came back and made more
repairs. But this time, the repairs "critically damaged the piping of the
Snow melt system, resulting in large portions of it being rendered unusable
... [and] result[ing] in leakage of propylene glycol onto passenger walkways
and such leakage has resulted in an injury to at least one third party..."
according to Healthone’s court suit.
Healthone discovered even more deficiencies, including more problems in
the snow melt system. "As a result of the defects in the design,
construction and improper repair of the snow melt system, at a minimum,
removal of the piping system and its replacement are required," Healthone
charged. Healthone also charged there were substantial problems with the
design and construction of the parking structure, including inadequate
sealing of the pipe penetrations, inadequate and defective joints in the
snow melt system and inadequate placement of Snow melt system pipes.
St. Paul Fire & Marine Insurance Company also filed their own civil suit
against Cobb Mechanical Contractors and others, claiming that Cobb was
negligent and "failed to use reasonable care in the selection of pipes,
joints, seals and other materials related to the de-icing structure [of the
snow melt system]... fail[ed] to use reasonable care in the installation and
construction of runoff collection devices and systems... [and] fail[ed] to
properly detect and repair..." the resulting defects.
St. Paul was suing, in part, because they were stuck with the bill for
over $18,000 in claims from twenty-eight owners of vehicles that were
damaged by the defective snow melt system. The various cracks in the parking
structure had allowed storm water, mixed with concrete leachate and de-icing
fluids, to drip onto cars and damage their exterior finish.
St Paul charged that Cobb Mechanical Contractor’s De-Icing and storm
water run off system was defective, because of numerous leaks, cracks,
ineffective patching of the cracks, use of substandard or inappropriate
piping and inadequate and deficient installation of the runoff handling
mechanisms to divert storm water. Cobb has responded to The Contractor’s
Critic in part, that they were a very minor part of this entire litigation.